Case Study - Cleveland Clinic , Abu Dhabi

Project data

  • Customer
  • Cleveland Clinic Abu Dhabi
  • Value
  • AED 28m
  • Area
  • 140,000 sq ft
  • Form of contract
  • Design & Build
  • Programme duration
  • 24 weeks
  • Completion date
  • June 2013
  • Architect
  • Perkins & Will

Overview

ISG were appointed by Cleveland Clinic as their fit out contractor for their office in Sowwah Square at Tower 3 levels 12, 13, 14,15,16,17 & 18.